In continuation of our letter dated March 28, 2025 and accordance with the provisions of Regulation 30 of SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, we are pleased to inform you that the project 'Construction of 4/6 Lane Southern Ayodhya Bypass from Km. 5.000 To Km. 37.172 (starting near Km. 112.540. ending at Km. 153.281 of NH-27) of Total Length of 32.172 Km on HAM Basis Under NHDP Phase-VII in the state of Uttar Pradesh.', executed through Ceigall Ayodhya Bypass Private Limited, subsidiary of the Company has received a letter dated 31st December 2025 from Independent Engineer (IE) certifying physical progress to tune of 20.09% of the Project highway till 29th December 2025. With this, project Milestone I under Schedule G of the Concession Agreement was successfully achieved.